In order to continue to live up to our position as global leaders, we are investing a good 20 million euros in new machinery, buildings and capacity.
Pattern shop: more secure storage for all your patterns/castings?
• workshop and storage area to be expanded and upgraded
Casting shop: increased melt capacity for even larger castings
• melt capacity to be increased to over 37 tonnes
• pattern area to be doubled in size, new mobile sand mixer to be provided
• building structure to be reinforced with the introduction of higher capacity travelling cranes
• storage hall for scrap and alloy stock to be expanded
Fettling shop: improved ergonomics for employee welfare
• an extraction unit to be installed for each grinding station and more effective noise reduction
• turntable and manipulator to be installed for grinding and/or burning larger castings
Quality control: more floor space dedicated to perfection
• an extra marking-out / measuring table to be purchased
• additional space for NDT inspection
New machining department: new machinery for up-to-date service
• new building to be set up with existing processing centres
• new vertical turning and boring mill with 4.7 m turning circle (provided with spindle and double column design)
• new 5-axes controlled milling and boring machine with machining length of 13 m
During this extensive investment period, you can of course continue to count on our full attention and service.